Browsing the September 2014 archive of Raising a Spiritual Home

September 28, 2014

Posted by MaryJo Lauer on 9/27/14

Thank the good Lord it only rained a little this week.  The masonry workers finished the east wall, except for a ten foot section (which will be used for lifts and other vehicles to get through to the nave area).  They have also started working on the gable end ... Read More »

September 21, 2014

Posted by MaryJo Lauer on 9/22/14

What a wonderful week – lots of sunshine and dry weather – perfect formula for getting outside work done.  Concrete was poured on Wednesday for the second floor choir loft and hallways.  Trusses over the upper north hallway have been put in place.  The decking on the two high ... Read More »

September 14, 2014

Posted by MaryJo Lauer on 9/13/14

Last week I reported the steps were poured but due to rain that pour was cancelled, though we did manage to get some concrete laid on some of the steps and three of the landings this week.  Steel workers have been slowed down with the rain and wind.  You ... Read More »

September 7, 2014

Posted by MaryJo Lauer on 9/06/14

We saw the skeleton structure of the bell tower go up last week but there was still much to be done.  Behind the scenes there is much welding being done, which consumes a lot of time.  This week you will see additional support beams added – crisscross beams for ... Read More »